A working protocol for buyers of machinery, electrical equipment and process lines who pay a deposit abroad: how to verify that a guarantee exists, read the effectiveness, reduction and expiry clauses that quietly empty it, write a demand that a bank must honour, and plan for a stop-payment application by the supplier.


A buyer orders a USD 1.2 million crushing and screening line. The contract asks for a 30% deposit, and the buyer, sensibly, asks for an advance payment guarantee. Three days later a PDF arrives by email: bank letterhead, a guarantee number, a signature, a stamp, and the words 'irrevocable and unconditional'. The deposit is wired. Eleven months later the line has not shipped, the supplier has stopped answering, and the buyer's lawyer sends the PDF to the bank named on it. The bank replies that it has no record of the instrument.
The scenario is illustrative, but the mechanism is well documented. In a March 2019 public service announcement, the FBI's Internet Crime Complaint Center warned that fraudsters use counterfeit SWIFT messages or documents, 'such as MT 799 or MT 760', to make fictitious bank instruments look legitimate. The ICC's Financial Investigation Bureau was warning about false bank guarantees as early as 2004, pointing to tell-tale wording such as validity of 'one year and one day' and guarantees described as 'divisible, assignable and transferable'. And a genuine guarantee can fail too: it can be worded so that it never comes into force, shrinks to nothing on the day of shipment, expires before the machine is commissioned, or can only be called with a document the supplier controls.
This protocol is for buyers of capital equipment and engineered packages from overseas suppliers: machine tools, presses, crushers, transformers and switchgear, pumps and compressors, packaging and process lines. It assumes the usual commercial structure, a deposit against an advance payment guarantee, a performance guarantee through acceptance, and a warranty guarantee or retention through the defects period, and it assumes the guarantees are issued subject to the ICC Uniform Rules for Demand Guarantees, URDG 758. The legal points are general; have the final wording checked by counsel under the law that will govern the guarantee.
What you are actually being offered
A demand guarantee is a bank's own promise to pay you on presentation of a complying demand. It is independent of the supply contract: the bank does not ask whether the supplier really breached, only whether your documents match the guarantee's terms. That independence is the whole point, and it is also why wording matters more than reputation. A guarantee from a first-class bank with a defective demand condition is worth less than a plain one from a second-tier bank.
| Instrument | Usual rules | Is payment independent of the contract? | What triggers payment | Typical buyer use |
|---|---|---|---|---|
| Demand guarantee (bank guarantee) | URDG 758 | Yes | A complying demand plus the documents named in the guarantee | Advance payment, performance and warranty security from the supplier's bank |
| Standby letter of credit | ISP98 (sometimes UCP 600) | Yes | Documents specified in the standby | Same purposes, common where the issuer is a U.S. bank |
| Surety bond (accessory or conditional bond) | Contract law of the bond; sometimes URCB 524 | No: the surety can raise the supplier's defences | Proof of default and loss, often an award or judgment | Rare in cross-border supply; slow and argued |
| Parent company guarantee | Contract law | Usually no | Proof that the subsidiary failed to perform | Useful only if the parent has reachable assets |
| Cash retention held by the buyer | Supply contract | Not applicable: you already hold the money | Buyer's own set-off right | Warranty security without any bank risk |
If the instrument offered is called a 'bond' or an 'insurance guarantee' and is issued by an insurer or a guarantee company rather than a bank, read whether it is payable on demand or only on proven default. A conditional bond can still be useful, but it is not the same security and should not be priced as if it were.
Three guarantees across one equipment contract
Each guarantee covers a different risk window. Gaps between those windows are where buyers lose money, so draw them on the project timeline before agreeing any wording.
| Guarantee | Amount (typical market practice) | Comes into force | Reduces | Should expire no earlier than |
|---|---|---|---|---|
| Advance payment guarantee (APG) | Equal to the advance, e.g. 30% of contract price | On receipt of the advance in the account named in the guarantee | Only by the value of equipment actually delivered and accepted, evidenced by documents you control | Final delivery of the items the advance financed, plus a margin of 60 to 90 days |
| Performance guarantee | Commonly 5% to 10% of contract price | On contract signature or the first payment | Usually does not reduce | Final or provisional acceptance (SAT or performance test), plus a margin |
| Warranty (defects liability) guarantee | Commonly 5% to 10%, often replacing a cash retention | On acceptance, often in exchange for releasing the performance guarantee | Usually does not reduce | End of the defects liability period, plus the time you need to discover, notify and present a demand |
The percentages are commercial norms, not rules. What matters is that no window is left open. The common gap is between shipment and acceptance: the APG reduces on shipment, the performance guarantee was set to expire on the original contractual delivery date, and the machine sits in the buyer's plant uncommissioned with no live security at all.


Trap 1: the guarantee that never came into force
Almost every APG contains an effectiveness clause: the guarantee 'shall become effective upon receipt by us of the advance payment in the amount of USD 360,000 to the account of [supplier] no. [X] held with us'. Banks insist on it, and it is fair: the bank should not guarantee the return of money that never arrived. It is also the most common way an APG ends up worthless.
Under URDG 758 article 7, a condition with no specified document to show compliance is disregarded, unless its fulfilment can be determined from the guarantor's own records. An effectiveness condition tied to an account held at the issuing bank is exactly that kind of condition: the bank checks its own books. If you pay the advance into a different account, at a different bank, under a different beneficiary name or in a different currency, the bank's records will not show the condition fulfilled, and the guarantee is not in force.
- Pay to the guarantee, not to the invoice. The account number, account name, bank and currency for the advance come from the guarantee text as received through your own bank, not from the proforma invoice or an email.
- Treat any account change as an APG question first. A request to pay the deposit to 'our other account', a Hong Kong account, or a related trading company means the guarantee will not activate, even if the request is genuine. If it is not genuine, it is a business email compromise attempt (see SourceRating's seller-entity check).
- Ask for confirmation of effectiveness. After the advance lands, ask the guarantor, through your bank, to confirm by authenticated message that the guarantee is in force. File the reply with the guarantee.
- Watch partial payments. If the clause names a single amount and you pay the advance in two instalments, the wording may never be satisfied. Write 'upon receipt of the advance payment, or of any part of it, up to the amount received'.
Trap 2: a PDF is not a guarantee you can verify
Banks exchange guarantees by authenticated SWIFT message. The issuing bank sends an MT760 (issuance of a guarantee or standby) to an advising bank, which can check the sender against its own relationship records before passing the text to you. Amendments travel as MT767, and a demand can travel back as MT765. An email attachment with a SWIFT-looking header proves nothing: anyone can type 'MT760' at the top of a page, which is exactly the pattern the FBI warning describes.
- Specify the channel in the contract: the guarantee is to be issued by authenticated SWIFT MT760 to the buyer's named bank (give the BIC) for advising to the buyer. Refuse delivery by email, courier only, or 'MT799 pre-advice'.
- Check the issuer, not just the name: look up the issuing branch's BIC in the SWIFT directory through your bank, and confirm the legal name of the bank matches the one in the guarantee. Lookalike names such as an invented 'International' or 'Investment' suffix on a real bank's name are a recurring feature of counterfeit instruments.
- Verify through your bank, never through the document: your bank's trade-finance team should confirm in writing that the MT760 was received from the stated issuer and that the authentication check passed. Do not call phone numbers or email addresses printed on the guarantee or supplied by the supplier.
- Compare the text: the operative text you received from your bank must be the same text the supplier sent you for approval. Differences in amount, expiry, effectiveness or demand conditions are amendments, and you have not accepted them.
- Check capacity: for large amounts, ask your bank whether it would add its confirmation or issue a counter-guaranteed local guarantee (below). A bank's reluctance to do so tells you something about the issuer.
Trap 3: the reduction and expiry clauses
Read the reduction clause as if you were the supplier trying to make the guarantee disappear. The usual weak form reduces the APG 'by the value of each shipment, upon presentation to us of a copy of the bill of lading'. The supplier holds the bill of lading. A shipment of the cheapest components, or of a shell crate, can reduce the APG by the invoice value assigned to it. And a copy bill of lading is easy to produce.
| Clause | Weak wording to reject | Wording to ask for |
|---|---|---|
| Reduction of APG | Reduced automatically on presentation of copy B/L or commercial invoice | Reduced only on presentation of a reduction statement signed by the buyer, or a delivery and acceptance certificate countersigned by the buyer, stating the value of items accepted |
| Expiry date | A fixed calendar date set to the contractual delivery date | A fixed calendar date set after the latest realistic acceptance date plus 60 to 90 days, with a contractual obligation on the supplier to extend if delivery slips |
| Expiry event | 'Upon shipment' or 'upon delivery of the goods' | A documentary event: presentation of a signed acceptance certificate. Avoid an event the bank cannot verify from documents |
| Place of presentation | The guarantor's head office in another country, paper only | The issuing branch or the advising bank, with presentation by authenticated SWIFT through the buyer's bank expressly permitted |
| Demand documents | A demand plus 'a certificate signed by the applicant', a court judgment, an arbitral award or an inspection certificate issued by the supplier's nominee | The demand and a beneficiary's statement of breach only (URDG 758 article 15) |
| Partial demands | Silent, or 'one demand only' | 'Multiple and partial demands permitted' |
| Governing rules | Not stated, or 'subject to the laws of [supplier's country]' only | 'Subject to URDG 758', with the governing law and forum stated |
Two further points come from the rules themselves. If a URDG guarantee states neither an expiry date nor an expiry event, article 25(c) ends it three years after issue, so an 'open-ended' guarantee is not open-ended. And article 23 lets a beneficiary present an 'extend or pay' demand: remember that this is legally a complying payment demand coupled with an alternative request for extension. In response, the guarantor may suspend payment for up to 30 calendar days while the supplier arranges an extension; if the extension is not granted within that window, the bank is legally bound to pay out immediately. It is the correct tool when acceptance has slipped and the expiry date is approaching, but buyers must understand it will trigger a cash payout if the bank or supplier declines to extend. Calendar the expiry at least 30 working days ahead, because an extension the supplier promises and the bank never issues is worth nothing on the expiry date.


Trap 4: demand conditions you cannot satisfy
URDG 758 article 15(a) requires that a demand be supported by the documents the guarantee specifies and, in any event, by a statement from the beneficiary indicating in what respect the applicant is in breach of the underlying obligations. The statement can be short; it does not have to prove the breach. Article 15(c) allows the guarantee to exclude even that statement. A guarantee that adds documents the supplier, an arbitrator or the supplier's appointed inspector must produce has turned an on-demand instrument into a conditional one.
The bank then has five business days after presentation to examine the demand (article 20). If it rejects, it must send a single rejection notice listing every discrepancy no later than the fifth business day (article 24); a guarantor that fails to do so is precluded from claiming the demand did not comply. Your job is to make the first presentation clean, because a corrected demand presented after expiry is too late.
- Present at the place stated in the guarantee, in the form it allows. Unless the guarantee expressly permits electronic presentation and states the format and address, present on paper: a signed original delivered by courier to the issuing branch, not an email.
- Have the demand signed by an authorised signatory of the beneficiary named in the guarantee. If your company has since changed its name or been merged, solve that before expiry.
- Quote the guarantee number and the issuing bank's reference exactly, and state an amount no higher than the current available amount after reductions.
- Include the statement of breach in the demand or as a separate signed document that identifies the demand. If the guarantee requires the signature to be authenticated by your bank, present through your bank.
- Keep proof of the time of delivery at the place of presentation, and present at least ten business days before expiry. Do not count on a public holiday or courier delay at the guarantor's location working in your favour.
A model demand, kept deliberately plain: 'We refer to your advance payment guarantee no. [number] dated [date] issued in our favour on behalf of [supplier]. We hereby demand payment of USD [amount]. [Supplier] is in breach of its obligations under contract no. [number] dated [date] in that it has failed to deliver the equipment listed in Schedule 1 by the contractual delivery date of [date] and has not refunded the advance payment. Please pay to account [details].' The SourceRating field playbook for this article contains the bilingual version, an extend-or-pay variant, and a reduction-statement template.
Trap 5: the supplier goes to court to stop payment
Independence has one recognised exception in almost every legal system: fraud. Under URDG 758 article 34, unless the guarantee says otherwise, it is governed by the law of the place of the issuing branch, so a guarantee issued in mainland China is governed by Chinese law. The Supreme People's Court's Provisions on the Trial of Independent Guarantee Disputes set out when a court may treat a demand as fraudulent and order the bank to suspend payment. Those provisions, in force since 1 December 2016, recognise independent guarantees and confine the exception. Article 12 lists the situations treated as fraud, including forged or false third-party documents, a judgment or award finding nothing is owed, and a beneficiary who has confirmed that the underlying obligation was fully performed and calls anyway. Under article 14, a stop-payment order requires a high probability that one of those situations exists, urgency with a risk of irreparable harm, and security from the applicant; and a court will not stop payment on the ground that the beneficiary itself breached the underlying transaction.
For buyers the practical consequences are straightforward. First, a supplier that wants to resist a call has a real procedure available in its home courts, and it will use it if the demand looks opportunistic. Second, do not sign anything during the project, such as a final acceptance certificate or a 'no outstanding claims' letter, that confirms full performance while you still intend to call. Third, your best defence is the documentary record behind your statement of breach: dated notices of delay, the factory acceptance test record, inspection reports and correspondence showing the supplier was told what was wrong and when. Build that file from the first missed milestone, not on the day you decide to call.
Where the amount justifies it, consider an indirect structure. Your own bank, or a bank in your country, issues a local guarantee in your favour, governed by your law and presentable at a branch in your city, backed by a counter-guarantee from the supplier's bank. The supplier pays more, and some suppliers' banks will refuse; but a call is then examined by a bank you can walk into, under a law your counsel knows, and the counter-guarantee dispute happens between banks.


Linking guarantees to inspection milestones
A guarantee is a backstop, not a payment schedule. It works best when payment milestones and reductions are tied to the same inspection evidence the buyer controls. For capital equipment, a workable structure looks like this.
| Milestone | Payment | Security in place | Evidence the buyer controls |
|---|---|---|---|
| Contract signature | Advance (e.g. 30%) to the account named in the APG | APG in force (confirmed by guarantor); performance guarantee issued | Authenticated MT760 via buyer's bank; effectiveness confirmation |
| Material and sub-supplier orders placed | None | APG at full value | Copies of major sub-orders; mill certificates for long-lead items |
| Factory acceptance test (FAT) passed | Progress payment (e.g. 30% to 40%) | APG still at full value | FAT protocol signed by buyer's inspector, with punch list |
| Shipment | Payment against documents, ideally under a letter of credit | APG reduced only by buyer-signed reduction statement | Pre-shipment inspection report; container or crate loading check |
| Site acceptance test (SAT) or performance test | Balance less retention | Performance guarantee returned in exchange for warranty guarantee | Signed acceptance certificate |
| End of defects liability period | Retention released, or warranty guarantee expires | None | Closed defect log |
The detail of the factory acceptance test, hold points and witness points is covered in SourceRating's ITP and EN 10204 3.2 protocol and the cross-border procurement field guide. The point here is narrower: every reduction or release of security should be triggered by a document that your inspector or your site team signs.
Contract clauses that make the guarantee obligation enforceable
- Form and issuer: 'The Seller shall procure an advance payment guarantee in the form of Appendix G, subject to URDG 758, issued by a bank acceptable to the Buyer and transmitted by authenticated SWIFT MT760 to [Buyer's bank, BIC]. No advance is payable until the Buyer's bank has confirmed receipt and authentication.'
- Account for the advance: 'The advance shall be paid only to the account named in the guarantee. Any request to pay to another account shall be made by the Seller's authorised signatory and shall be accompanied by an amended guarantee naming that account.'
- Extension obligation: 'If acceptance has not occurred 45 days before the expiry of any guarantee, the Seller shall procure its extension by not less than 90 days. Failure to do so is a breach entitling the Buyer to demand payment in full.'
- Reduction only by Buyer document: 'The advance payment guarantee shall reduce only on presentation of a reduction statement signed by the Buyer stating the value of equipment delivered and accepted.'
- No set-off of guarantee costs: 'All charges of the issuing bank, any confirming bank and any counter-guarantor are for the Seller's account.'
- Replacement on downgrade: 'If the issuing bank's long-term credit rating falls below [rating], the Seller shall within 30 days provide a replacement guarantee from an acceptable bank.'
Before you release the deposit: a checklist
- The guarantee text matches the agreed form in Appendix G word for word, including amount, currency, beneficiary name and contract reference.
- It is subject to URDG 758, and the governing law, place of presentation and form of presentation are stated.
- It arrived as an authenticated SWIFT MT760 through your own bank, and your bank has confirmed the authentication in writing.
- The issuing bank's legal name and BIC have been checked through your bank, not through contact details on the document or in the supplier's email.
- The effectiveness clause names an account, and that is the account, bank, beneficiary and currency on your payment instruction.
- Reduction requires a document you sign; no reduction on supplier-issued documents.
- Expiry is after the latest realistic acceptance date plus a margin, and the contract obliges the supplier to extend.
- Demand requires only a demand and a statement of breach; no judgment, award, applicant certificate or third-party certificate.
- Multiple and partial demands are permitted.
- The expiry date and an extension reminder 30 working days earlier are in your contract-management calendar, with a named owner.
- The project file holds the dated delay notices, inspection reports and correspondence you would need to support a statement of breach.
None of this is hostile to a good supplier. A manufacturer with a real balance sheet and a real banking relationship can issue a URDG guarantee by MT760 in a few days, and most experienced exporters have done it many times. The suppliers who find these requests unreasonable are, disproportionately, the ones the deposit protection was meant for. If you need help reviewing a guarantee text or structuring payment milestones around inspection, contact SourceRating with the draft contract and the guarantee wording.
Reading notes
Rules, court provisions and fraud warnings
Primary sources checked on 20 November 2026. URDG 758 article references are to the ICC 2010 revision; the full rule text is an ICC publication. This article is general information, not legal advice.
Supreme People's Court of the People's Republic of China
Fa Shi [2016] No. 24, effective 1 December 2016; article 12 (fraud situations) and article 14 (stop-payment conditions).
FBI Internet Crime Complaint Center (IC3)
Public service announcement on counterfeit SWIFT MT 799 and MT 760 messages used to legitimise fake instruments.
ICC Commercial Crime Services
2004 ICC Financial Investigation Bureau warning on false bank guarantees and the wording that gives them away.
ICC Store
The official rule text most international bank guarantees are issued under; articles 7, 15, 20, 23, 24, 25 and 34 are discussed above.
Continue the decision
Related buyer guides
The PO Names a Factory. The Invoice Names a Trader. Who Is the Seller?
Checking that the contracting party, the invoicing party and the payee are the same entity.
The Cross-Border Procurement Field Guide
The wider procurement lifecycle, including L/C and T/T payment structures.
The 3.2 Certificate Has Two Signatures. Did Either Inspector See the Test Bar Cut?
Building an ITP whose hold points can drive payment and guarantee reductions.
The Carrier Supports an eBL. Can Your Buyer Actually Collect the Cargo?
Why a copy bill of lading is weak evidence for releasing money or security.